Element Park

Project Description:
Element Park – Clyde North $600,000
Project Date:
2024 (4 month project)
Project Type:
Sub- Contractor
Project Client:
MAB Constructions Pty Ltd
Project Features:

Site area 1,070 m2

Cut to fill excavation 450 m3.

Import type A 250m3.

Asphalt pavement 300m2

Concrete Footpath 250m2

Kerb and channel 115 lin.m

Storm Water 30 lin.m

Line Marking, Signage, Topsoiling