GYG Carrum Downs

Site area 1,530 m2 Cut to fill excavation 440 m3. Asphalt pavement 615m2 Concrete Footpath 155m2 Kerb and channel 145 lin.m Line Marking, Signage, Topsoiling

Element Park

Site area 1,070 m2 Cut to fill excavation 450 m3. Import type A 250m3. Asphalt pavement 300m2 Concrete Footpath 250m2 Kerb and channel 115 lin.m Storm Water 30 lin.m Line Marking, Signage, Topsoiling

Mclister Street

Demolition of existing perimeter roads.Concrete footpath 30m2.Kerb and channel 400m2.Storm water drainage 200lin.mSignage, line marking, bollardsAsphalt pavement 1,200m2.External concrete 400m2Bus sheltersRoot barrier between transmission gas line and future trees

Emerald

Bulk Earthworks 100 cut, 500 fillAsphalt pavement 900 m2Kerb and channel 230 lin.mConcrete driveway 160 squares (m2)storm water drainage 226 lin.mWater, Electrical and NBN reticulation.

Ringwood Secondary College

Bulk earthworks – 800 m2Kerb and channel – 450 lin.mAsphalt 1,300m2.Light duty concrete pavement footpath 1,200m2Basketball court 1,250m2Trench grates

Aldi- Stage 2 (Homemaker Centre)

External DemolitionExternal hard standHeavy duty concrete pavement 250m2Exposed light duty footpath 220m2Line marking, bike hoops.Storm water drainageTrench grates

Chadstone Home Maker Centre

External DemolitionBulk earthworks cut 1,200m21,300 m2 asphalt pavement550 m2 light duty exposed pavementTree removalRetaining wall 1,400 lin.mKerb and channel 450 lin.mGuard railLine Marking, wheel stops, bollards, trolly bays and bike hoop’s.Storm water drainageTrench grates

Coles Traralgon

Site area 2,000 m2Cut to fill excavation 4,500 m3.Import type A 5,000m3.Asphalt pavement 8,200m2Heavy duty concrete 1,300m2Concrete pavement light duty 1,600 m2Kerb and channel 1,100 lin.mRetaining walls 450 lin.mStorm Water 1,200 lin.mTrench gratesLine Marking and bollards and wheel stops.

Towerhill IGA

Demolition of existing pavements2,400 m2 of asphaltKerb and channel-320 lin.mLight duty Exposed concrete 330 m2Line MarkingTrench grates