Mclister Street

Project Description:
Union Quarter Road Reconstruction - $1.5M
Project Date:
2023 (8 month project)
Project Type:
Head Contractor
Project Client:
Bujar Pty Ltd
Project Features:

Demolition of existing perimeter roads.
Concrete footpath 30m2.
Kerb and channel 400m2.
Storm water drainage 200lin.m
Signage, line marking, bollards
Asphalt pavement 1,200m2.
External concrete 400m2
Bus shelters
Root barrier between transmission gas line and future trees